The UK gigafactory story has narrowed to two cell makers: AESC in Sunderland, which opened a second plant in 2025, and Agratas in Somerset, which is building the largest planned UK site. Together they account for most of the cell capacity announced for the UK, and both sit beside a single anchor carmaker.
This analysis sets out the projects and their published capacities, compares them with the demand outlook the government has used, and considers what the gap means for component, materials and service suppliers. All figures are as published in the sources cited; capacity is shown in gigawatt hours (GWh) of cells a year.
The UK gigafactory projects at a glance
| Site | Published capacity | Status and support |
|---|---|---|
| AESC UK plant 1, Sunderland | 2GWh (UK battery strategy, November 2023) | Operating; supplies Nissan |
| AESC UK plant 2, International Advanced Manufacturing Park, Sunderland | 15.8GWh a year, enough for up to 100,000 EVs | Opened by December 2025; £1 billion financing package and £150 million Automotive Transformation Fund grant announced May 2025 |
| Agratas, near Bridgwater, Somerset | About 40GWh once all phases are complete | Under construction; capital grant of up to £380 million unveiled April 2026; anchor customer JLR |
The AESC plant 2 figures come from the government’s announcement of 9 May 2025, in which the National Wealth Fund and UK Export Finance guaranteed £680 million of bank lending and a further £320 million came from private finance and AESC equity. UK Export Finance records the plant’s capacity as 15.8GWh a year, adjacent to the existing plant. A government release of 16 December 2025, on the start of next-generation Nissan Leaf production, said AESC had opened the 15.8GWh gigafactory across the road from Nissan’s plant.
Agratas, a Tata Group company, was announced in July 2023 as a £4 billion-plus, 40GWh investment, with production then due to start in 2026. In its January 2026 report on the proposed subsidy, the Subsidy Advice Unit described the plan as about 40GWh by 2035 once all phases are complete, backed by roughly £5 billion of private capital, with the grant paid in phases against milestones. On 9 April 2026 the Business Secretary unveiled the £380 million grant and Agratas said it expected more than 2,200 people on site over the following year. As of November 2026, no public source checked for this article gave a confirmed date for first cell production at Somerset.
How capacity compares with demand
The government’s UK battery strategy, published in November 2023, uses the Faraday Institution’s 2022 UK gigafactory outlook. It forecasts annual UK demand for battery manufacturing capacity of over 100GWh in 2030, mainly for cars and light commercial vehicles, and nearly 200GWh by 2040 across cars, vans, heavy vehicles, buses and grid storage. Within that, light commercial vehicles were projected to need around 10GWh in 2030 and 25GWh by 2040.
Set against those projections, the announced UK gigafactory capacity of about 58GWh (2GWh plus 15.8GWh plus around 40GWh) would cover a little over half of the 2030 figure, and only once Agratas reaches full output, which the subsidy report places at 2035. The forecast itself dates from 2022, before later changes to vehicle production and policy, so it should be read as an order of magnitude rather than a target. The Subsidy Advice Unit report records the government’s view that estimated UK demand in 2035 will exceed AESC’s future production and that rules of origin add pressure to localise battery supply.
That pressure is specific. From 1 January 2027, the UK and EU trade agreement requires electric vehicles traded between them to contain an originating battery pack, which makes local cells, or cells from the EU, more valuable to UK vehicle plants. Origin is a value calculation across the whole chain, as discussed in our article on why country of assembly is not a complete origin assessment.
Where the value sits in a battery
A cell plant is only one stage. The battery strategy, citing Roland Berger, breaks down the approximate value of a lithium-ion pack as follows:
- cathode mining and primary processing: 23 percent;
- secondary cathode processing into active material: 11 percent;
- anode mining and processing: 8 percent;
- other cell materials: 11 percent;
- cell manufacture: 21 percent;
- module and pack materials, battery management system and pack assembly: 26 percent combined.
The strategy notes that the cathode makes up over 40 percent of the value of a cell. A UK gigafactory that imports its cathode material therefore localises a minority of the pack’s value, which is why midstream processing is treated as a separate investment priority.
What it means for UK suppliers
For suppliers, the projects create demand in three layers: construction and equipment during build, consumables and services once lines run, and materials that are harder to localise. Generic examples include factory automation and maintenance, dry-room and environmental control services, logistics and packaging for cells and modules, quality and metrology, scrap handling and recycling, and training.
Public support is available alongside. The government’s DRIVE35 programme, launched in July 2025 with £2.5 billion, explicitly covers gigafactories and their supply chains, and a December 2025 announcement set out regional EV supply chain pilots in the North East and West Midlands. Skills are a constraint: Skills England introduced a shorter battery manufacturing apprenticeship unit in March 2026 to serve the Somerset site and the wider sector.
Qualification takes time. Cell plants scrap and rework expensive material, so new suppliers are judged on yield impact as well as price; our articles on battery factory yield and local sourcing on landed cost and capability cover how buyers are likely to assess them.
Key points for suppliers and manufacturers
- Announced UK gigafactory capacity is about 58GWh across AESC’s two Sunderland plants and Agratas in Somerset, with Agratas reaching about 40GWh by 2035.
- The demand outlook the government has used points to over 100GWh by 2030 and nearly 200GWh by 2040, so announced capacity covers a little over half of the 2030 figure.
- Rules of origin from 1 January 2027 raise the value of locally made cells and packs for UK vehicle plants.
- Cathode material is over 40 percent of cell value and remains largely outside these projects.
- DRIVE35 funding and new apprenticeship routes support suppliers entering the chain.
Sources
- GOV.UK: UK battery strategy (November 2023)
- GOV.UK: Another boost for British car industry as £1 billion secured for new Sunderland gigafactory
- UK Export Finance: Category B project supported, AESC EDG, UK
- GOV.UK: Nissan launches £450m next-generation LEAF
- GOV.UK: Tata Group to invest over £4 billion in UK gigafactory
- CMA Subsidy Advice Unit: Report on the proposed subsidy to Agratas Limited
- GOV.UK: Business Secretary champions flagship investment in UK’s largest gigafactory
- GOV.UK: Government launches £2.5bn DRIVE35 programme
- Skills England: New apprenticeship unit to supercharge battery manufacturing
Sources checked in November 2026. Rules, rates and schemes can change after publication, so check the linked official pages before acting.