APQP explained: the five phases of product quality planning

APQP sets the outputs each development phase must deliver before volume production. Run real gate reviews, link FMEAs to the control plan, and check which manual edition each customer requires.

Email story
Technician measuring a metal component with a digital caliper beside technical drawings on screens
Illustrative photograph · TECNIC Bioprocess Solutions / Unsplash

APQP, or Advanced Product Quality Planning, is the structured method automotive customers use to make sure a supplier has planned, built and proven a new part and its manufacturing process before volume production starts. It sets out what each stage of development must produce and gives customer and supplier a shared language for launch readiness.

This guide explains the five-phase structure most supply chains still use, the outputs and gates in each phase, and how the method connects to the FMEA, the control plan and the Production Part Approval Process (PPAP). It also covers what changed when AIAG published a third edition in March 2024, which matters to any UK supplier whose customers have updated their requirements.

What APQP is and who maintains it

The Automotive Industry Action Group (AIAG) publishes the reference manual. Its APQP overview describes the method as defining the required inputs and outputs for each stage of product development, and as a way for customers to communicate their quality planning requirements to suppliers. It is one of the six quality core tools AIAG lists alongside the control plan, PPAP, FMEA, measurement system analysis (MSA) and statistical process control (SPC).

The process grew out of supplier quality planning work by the North American vehicle makers. Quality-One, a consultancy, summarises in its APQP guide that the OEMs published a common process in 1994 and updated it in 2008. Many OEMs add customer-specific requirements, so a supplier should always read the manual alongside its customer’s own launch procedures.

For IATF 16949 certified sites, AIAG’s overview of the core tools in IATF 16949:2016 notes that clause 8.3.4.1 expects periodic updates on customer quality planning milestones, gate reviews and open issues, and that clause 9.1.1.2 links statistical tools chosen during planning to the risk analysis and control plan.

The five phases of APQP

The widely used five-phase model, as set out by Quality-One, is summarised below. Section 0, pre-planning, often comes before phase 1.

Phase Purpose Typical outputs
1. Plan and define Turn customer needs into design and quality goals Design, reliability and quality goals; preliminary bill of materials and process flow; preliminary special characteristics; product assurance plan
2. Product design and development Prove the design meets requirements Design FMEA; design for manufacture and assembly; design verification and review; prototype control plan; drawings and specifications; team feasibility commitment
3. Process design and development Plan a capable manufacturing process Process flow chart; floor plan; characteristics matrix; process FMEA; pre-launch control plan; process instructions; MSA plan
4. Product and process validation Prove the process at rate Significant production run; MSA results; capability studies; PPAP; production validation testing; packaging evaluation; production control plan; quality planning sign-off
5. Feedback, assessment and corrective action Learn and reduce variation after launch Reduced variation; improved delivery and customer satisfaction; lessons learned

The phases overlap in practice. Process design usually starts before the product design is frozen, which is why change control matters so much during a launch. The disciplines in engineering change control on the shop floor apply from phase 2 onwards.

Gates, sign-off and the role of risk

Each phase ends with a review, often called a gateway, at which the team and the customer agree whether the outputs are good enough to move on. A gate is only useful if it has defined entry criteria and someone with authority to say no. A practical gate review checks:

  • that required outputs exist and are at the agreed revision;
  • which open issues remain, who owns them and by when they close;
  • whether risks in the FMEA have actions with dates, not just ratings;
  • whether tooling, gauges and supplier parts are on track for the next phase;
  • whether the customer’s own launch milestones are still achievable.

The third edition puts more weight on this. AIAG’s product page for APQP 3rd edition lists new sections on sourcing, change management, programme metrics, risk assessment and mitigation plans, and gated management, along with updates reflecting agile product management and new material on part traceability.

How the method links to FMEA, the control plan and PPAP

The core tools are designed to work as one system. The design FMEA is produced in phase 2 and the process FMEA in phase 3. Their actions feed the control plan, which develops from a prototype version through a pre-launch version to the production control plan in phase 4. AIAG’s core tools overview notes that IATF 16949:2016 links control plan updates to PFMEA updates and brings customer approval of control plans into the requirements.

PPAP sits inside phase 4. Quality-One describes it as evidence that the planning work has been done, since the submission draws together design records, FMEAs, the control plan, MSA studies, capability results and samples from the significant production run. AIAG’s PPAP manual page describes the process as setting the minimum a supplier must document and submit before the customer approves shipment of production quantities.

Measurement is often the weak link. If gauges cannot repeat, capability results and PPAP evidence mean little, a point explored in dimensional inspection and measurement repeatability.

What changed with the third edition

AIAG’s quality core tools page lists the third edition of the planning manual and a first edition of a standalone Control Plan manual, both published in March 2024. Control plan content was removed from the planning manual and moved into the new document, which adds a safe launch requirement to control plan phases and guidance for highly automated processes. The same page lists a harmonised AIAG and VDA SPC manual published in July 2026.

For suppliers, the practical steps are to check which edition each customer requires for new launches, update internal launch procedures and templates, and retrain launch teams on the new gate and risk sections. Where customers still work to the earlier edition, a supplier may need to run both for a period. Supplier quality teams can use the changes as a prompt to review how they support sub-tier suppliers through launch, building on supplier development as a shared production problem.

Key points for launch and quality teams

  • APQP defines what each stage of product development must produce and how customer and supplier agree readiness.
  • The five phases run from plan and define to feedback and corrective action, with gate reviews between them.
  • Design and process FMEAs feed the control plan, and PPAP in phase 4 draws the evidence together.
  • AIAG published the third edition and a standalone Control Plan manual in March 2024; check which edition each customer requires.
  • Gates work only with defined criteria, named owners for open issues and the authority to stop a launch.

Sources